Site leadership and quality · Handover

Handover between foremen at shift and phase changes

At a shift change, the outgoing foreman passes on live permits, unfinished welds and open purge, open ends and safety conditions, ideally face to face at the workface. At a phase change or when a foreman leaves, the handover covers the full state of the work packages, records and open issues, in writing, with time for the new foreman to walk the site.

Shift-change handover

  • Permits: which are open, their conditions, and whether they carry over or must be closed.
  • Work in progress: welds started or tacked, lines under purge, joints waiting for examination.
  • Open ends: which are bagged or capped, and any that need checking.
  • Safety: isolations in place, barriers, fire watch status, near misses on the shift.
  • Issues: material shortages, drawing questions, holds from QA/QC.
  • People: who is absent, who is new, anyone working outside their usual task.

Phase change or foreman replacement

What to hand over when a foreman leaves or a phase ends
ItemWhat the incoming foreman needs
Work package statusWhich lines and spools are complete, in progress and not started, by number
As-built mark-upsField changes marked on isometrics and not yet issued
Punch listOpen items, who raised them, agreed fixes
Open NCRs and holdsStatus and the agreed actions, from QA/QC
Permits and accessOngoing permit arrangements, access restrictions, contacts
CrewSkills, qualification limits, language needs, who leads in each area
RelationshipsOwner area contacts, other trades’ foremen, recurring friction

Running it well

  1. Agree the handover format before the first shift change, using the daily report template where possible (foreman daily reports).
  2. For shift changes, overlap enough time to walk the open work together.
  3. For a phase change or departure, plan an overlap of days, not minutes, if the schedule allows it.
  4. Have QA/QC confirm the open NCR and hold list, so quality items are not passed on from memory.
  5. Both foremen sign the written handover, and the site manager keeps it.

Where the owner and site rules decide

Permit systems often require permits to be closed or formally transferred at shift change, and some owners require a named supervisor to be present before any work resumes. Turnover documents for completed systems follow the owner’s format (turnover package). Check the rules rather than relying on the foremen’s habits from previous sites.

When the foreman change is planned, tell the crew in advance who the new foreman is and when they start, and introduce them on site. A crew that learns about the change on the day loses time and confidence, and small habits the previous foreman enforced, such as checking bagging at the end of the shift, can lapse in the first week.

Language at handover

If the two foremen do not share a first language, the written handover is the reliable part. Keep it short and specific, with line and weld numbers, and have a bilingual person present for the walk-through (mixed-language crews).

Frequently asked questions

Can a permit pass from one foreman to the next?

Only if the owner’s permit system allows a formal transfer. Many require the permit to be closed and a new one issued, so check before the shift ends.

Who is responsible for the work during the handover?

Agree it in advance; normally the outgoing foreman until the handover is signed. Unclear overlap is when things get missed.

What if the outgoing foreman leaves before a handover?

Have QA/QC and the site manager rebuild the status from the daily reports, weld log and a site walk before work resumes in that area.