Shift-change handover
- Permits: which are open, their conditions, and whether they carry over or must be closed.
- Work in progress: welds started or tacked, lines under purge, joints waiting for examination.
- Open ends: which are bagged or capped, and any that need checking.
- Safety: isolations in place, barriers, fire watch status, near misses on the shift.
- Issues: material shortages, drawing questions, holds from QA/QC.
- People: who is absent, who is new, anyone working outside their usual task.
Phase change or foreman replacement
| Item | What the incoming foreman needs |
|---|---|
| Work package status | Which lines and spools are complete, in progress and not started, by number |
| As-built mark-ups | Field changes marked on isometrics and not yet issued |
| Punch list | Open items, who raised them, agreed fixes |
| Open NCRs and holds | Status and the agreed actions, from QA/QC |
| Permits and access | Ongoing permit arrangements, access restrictions, contacts |
| Crew | Skills, qualification limits, language needs, who leads in each area |
| Relationships | Owner area contacts, other trades’ foremen, recurring friction |
Running it well
- Agree the handover format before the first shift change, using the daily report template where possible (foreman daily reports).
- For shift changes, overlap enough time to walk the open work together.
- For a phase change or departure, plan an overlap of days, not minutes, if the schedule allows it.
- Have QA/QC confirm the open NCR and hold list, so quality items are not passed on from memory.
- Both foremen sign the written handover, and the site manager keeps it.
Where the owner and site rules decide
Permit systems often require permits to be closed or formally transferred at shift change, and some owners require a named supervisor to be present before any work resumes. Turnover documents for completed systems follow the owner’s format (turnover package). Check the rules rather than relying on the foremen’s habits from previous sites.
When the foreman change is planned, tell the crew in advance who the new foreman is and when they start, and introduce them on site. A crew that learns about the change on the day loses time and confidence, and small habits the previous foreman enforced, such as checking bagging at the end of the shift, can lapse in the first week.
Language at handover
If the two foremen do not share a first language, the written handover is the reliable part. Keep it short and specific, with line and weld numbers, and have a bilingual person present for the walk-through (mixed-language crews).