Questions and what to listen for
| Question | Good answers include | Warning signs |
|---|---|---|
| Walk me through how you planned the last week of a job you ran. | Work packages, crew allocation, permits requested ahead, material checks | Only “I told people what to do” |
| Your hot work permit is refused at 7 a.m. What do you do? | Finds out why, reassigns the crew to permitted work, reports the delay | Starts anyway, or waits idle without reporting |
| A welder wants to skip post-purge because the shift is ending. What happens? | Stops it, explains why, checks the weld with QA/QC | Treats purge as optional |
| How did you check that only qualified welders were welding? | Checked a qualification list or with QA/QC before assigning | Assumed everyone was qualified |
| Tell me about a conflict with another trade in a shared area. | How the conflict was resolved, who was involved, what changed | Blames the other trade only |
| What goes into your daily report? | Manpower, progress against plan, issues, permits, safety observations | Cannot describe one |
Scenario test
Give the candidate a short isometric set and a crew list, and ask them to plan the first two days: what they would check before welding, which permits they need and what they would tell the crew. Twenty minutes is usually enough to see whether they think ahead. For candidates in Korea this works by video with shared documents.
Run the interview with the person the foreman will report to, not only HR, and agree beforehand what a good answer to each question looks like. Score answers against that, rather than on overall impression, so candidates interviewed in different weeks or with an interpreter are compared fairly. If an interpreter is used, ask them to translate the candidate’s words closely, not summarise them, because the detail is what you are assessing. Keep notes of the answers; they help if you need to compare a later candidate.
Questions specific to fab work
- How do you keep open tube ends clean overnight, and how do you check the crew did it?
- What changes when you move from bulk distribution to tool hook-up in an occupied fab?
- How do you work with QA/QC when they reject a weld your crew made under schedule pressure?
- Which owner rules have you had to enforce in a cleanroom?
Where the owner and your organisation decide
The owner’s site rules may require the foreman to hold safety training or a supervisor card before signing permits, and your organisation decides how much authority the foreman has over hiring, discipline and overtime. Tell the candidate what the role can and cannot decide, and ask whether they have worked under similar limits.
Using the profile
On a WELDK profile, each item is marked candidate-provided, reviewed or employer-tested. Start with the items that matter for your scope and are only candidate-provided, such as crew size led, and confirm them with detailed questions (how to read a profile).