Working back from move-in
- Get the tool move-in schedule and the first hook-up dates.
- Allow time for induction and supervised first work.
- Add travel and arrival time.
- Add the hiring lead time, including work authorization (what sets the timeline).
- Plan useful work for early arrivals: distribution, prefabrication, support installation.
| Change | Option |
|---|---|
| Tools arrive later | Move crew to distribution or prefabrication |
| Tools arrive earlier | Increase hours or bring forward the next group |
| Hook-up drawings late | Use the time for training and mock-ups |
Tell candidates early
Changes to start dates should be confirmed in writing to candidates as soon as you know them. Date changes do not need a new test, but long delays can affect availability.