UHP piping · Schedule

Fitting a UHP crew’s start into tool move-in and hook-up windows

Plan the start date from the tool move-in schedule, not the hiring date: hook-up crews are needed when tools are set and ready for connection, and distribution crews before that. Allow for the hiring and travel lead time, build in a short induction, and keep a few weeks of float, because tool move-in dates often shift.

Working back from move-in

  1. Get the tool move-in schedule and the first hook-up dates.
  2. Allow time for induction and supervised first work.
  3. Add travel and arrival time.
  4. Add the hiring lead time, including work authorization (what sets the timeline).
  5. Plan useful work for early arrivals: distribution, prefabrication, support installation.
If dates move
ChangeOption
Tools arrive laterMove crew to distribution or prefabrication
Tools arrive earlierIncrease hours or bring forward the next group
Hook-up drawings lateUse the time for training and mock-ups

Tell candidates early

Changes to start dates should be confirmed in writing to candidates as soon as you know them. Date changes do not need a new test, but long delays can affect availability.

Frequently asked questions

What do early arrivals work on?

Distribution runs, prefabrication and support installation, so their first weeks are productive while tools are still being set.

What if a candidate cannot wait for a delayed start?

Discuss it openly. You may need to replace them; plan backups for critical roles.

Who tells candidates about a delay?

The employer, who made the offer. Put changes in writing.