Site leadership and quality · Inspection planning

Inspection and hold points to set for a new welding crew

For a new crew, add points where work stops until someone checks it: before the first production weld, after the first welds on each setup, before closing any joint that cannot be inspected later, and before pressure or leak tests. Set them in the inspection and test plan with the owner, and relax them only on evidence that the crew’s work is consistently acceptable.

Hold, witness and review points

A hold point means work may not continue until the named party has inspected and released it. A witness point means the party is notified and may attend, but work can proceed if they do not. A review point is a check of records. Your inspection and test plan (ITP) names who holds each point: contractor QA/QC, the owner’s inspector or both.

Points often added for a new crew (agree the final list in the ITP)
PointTypeWhat is checked
Before first production weldHoldQualification on file, correct WPS or weld schedule, equipment calibration, purge set-up
First welds on each machine setupHoldVisual and borescope examination of sample or first welds
Start of each shiftWitness or reviewSample weld if the owner specification requires one
Before a joint becomes inaccessibleHoldExamination of welds that will be closed in, insulated or built over
Material change or new size rangeHoldQualification range and procedure match
Before pressure or leak testHoldWeld log complete for the boundary, all welds examined

Setting them up

  1. Start from the owner’s ITP or inspection requirements and your quality plan.
  2. Add the new-crew points above for an agreed period or number of welds.
  3. Agree notice times with the owner’s inspector so hold points do not stall the crew.
  4. Brief the foreman and crew on what stops work and who releases it.
  5. Record each release with name, date and weld numbers.

Relaxing them

Decide the release criteria up front, for example a number of consecutive acceptable welds per welder and setup, as agreed with your QA manager and the owner. Base the decision on the crew’s actual records (reject rate tracking), not on time elapsed. Code-required and owner-required points stay regardless.

Making hold points work on site

Hold points fail when nobody knows they exist or nobody comes to release them. Put the hold points on the work package or traveller the crew uses, so the welder sees them at the joint. Give the foreman the names and contact details of the people who can release each point, and agree what happens out of hours. If the owner’s inspector cannot attend within the agreed notice, record the request and the delay; that record protects the crew and the schedule.

Where the owner and code decide

ASME B31.3 sets required examinations and the owner’s inspector’s right to inspect; the owner specification and ITP set the hold points that are mandatory. Your additional new-crew points are your own control and can be adjusted, but tell the owner if you change them, since they may rely on them.

Frequently asked questions

Will hold points slow the new crew down?

Some, at first. Agreeing response times and grouping inspections reduces the delay, and catching a setup problem on the first welds is faster than repairing a whole line.

Who can release a hold point?

The party named in the ITP. If that is the owner’s inspector, contractor QA/QC cannot release it alone.

Do hold points apply to pipe fitters too?

They can, for example fit-up checks before welding on critical lines. Include them if your owner or quality plan calls for fit-up inspection.

Have a fab scope that needs these trades?