Bagging, capping and labelling rules to brief new pipers on

Brief new pipers on three rules on day one: components stay in their original bags until the point of installation, every open tube end is capped whenever work stops, and every line and open end is labelled as the specification requires. These rules prevent most contamination, so check them daily in the first weeks.

Rules to brief (your specification may add more)
RuleIn practice
Bagged until useOpen the bag at the work point, not in the storage area
Damaged bagReport; component may need inspection or replacement
Cap open endsEvery time work stops, including breaks
Clean glovesChange when contaminated
Label linesGas or chemical name, flow direction, line number
Label open endsShow the line and that it is open

How to brief

  1. Show the rules with real components and caps at the induction.
  2. Give a one-page summary with pictures.
  3. Check during the first shifts and correct immediately.
  4. Repeat when the crew moves to a new area or system.

See also cleanroom experience.

Frequently asked questions

Do caps need to be new?

Follow the specification. Many sites require clean caps from controlled stock.

Who checks the labels?

The crew labels; the supervisor and QA check during walkdowns.

Are the rules the same for plastic lines?

The principle is the same — keep clean and closed — but the specification for each system decides the details.