Before the test
- Section isolated with the right fittings or caps.
- Test port connections installed and clean.
- Every joint accessible, with insulation or covers not yet fitted.
- Joint and weld numbers on the line match the records.
- Any temporary fittings removed or recorded.
| Leak at | Usual fix | Then |
|---|---|---|
| Face-seal fitting | Remake with a new gasket; check sealing surfaces | Retest |
| Weld | Repair or cut out per the welding procedure | Retest and record |
| Component | Replace the component | Retest |
Limits come from the specification
Leak rate limits and test methods are set by the owner specification, often referencing SEMI F1 for high-purity gas systems. Do not quote a figure from another project.