| Step | Piping crew’s part | Usually run by |
|---|---|---|
| Pressure test | Set up blinds and gauges, pressurise per procedure | Contractor QA, witnessed by the owner’s inspector where required |
| Helium leak test | Isolate, connect, fix leaks | Test team or QA |
| Purge | Connect purge gas, open and close valves per plan | Contractor |
| Purity certification (particles, moisture, oxygen) | Access and connections | Specialist certifier |
| Turnover | Walkdown, punch items, records | Contractor and owner |
Records
Each step leaves records: test reports, leak test results, purge logs and certification. Pipers make sure line numbers and joint numbers match. The QA team assembles the package (turnover package).
Common delays
- Open punch items found at the walkdown.
- Records that do not match the installed line.
- Leaks found late because joints were covered too early.