UHP piping · Turnover

Pressure test, purge and turnover: the piper’s part before handover

Before a UHP line is handed over it is usually pressure tested, leak tested, purged with clean gas and certified for purity by a specialist, in the order and to the limits the owner specification sets. The piping crew prepares and restores the line at each step, fixes any faults found, and supports the turnover records.

Before handover (typical order; specification decides)
StepPiping crew’s partUsually run by
Pressure testSet up blinds and gauges, pressurise per procedureContractor QA, witnessed by the owner’s inspector where required
Helium leak testIsolate, connect, fix leaksTest team or QA
PurgeConnect purge gas, open and close valves per planContractor
Purity certification (particles, moisture, oxygen)Access and connectionsSpecialist certifier
TurnoverWalkdown, punch items, recordsContractor and owner

Records

Each step leaves records: test reports, leak test results, purge logs and certification. Pipers make sure line numbers and joint numbers match. The QA team assembles the package (turnover package).

Common delays

  • Open punch items found at the walkdown.
  • Records that do not match the installed line.
  • Leaks found late because joints were covered too early.

Frequently asked questions

Who decides the test pressure?

The design and the code or specification. The crew follows the approved test procedure.

Can purge be done before the leak test?

Follow the order in the specification; testing first usually avoids repeating the purge.

What is a punch item?

An outstanding defect or task found during inspection that must be closed before handover.