A weld map marks every weld on the isometric with a unique number; the weld log records, for each number, who welded it, with which procedure and material, when, and how it was examined. A QA/QC hire should keep both current every day, so any weld can be traced from the drawing to the welder, the material and the inspection result.

What each record holds

Typical content of fab weld records (the owner specification sets the final list)
RecordTypical contentUpdated by
Weld mapIsometric or drawing with a unique number for each weld, revision, line and system IDQA/QC or document control, as drawings change
Weld logWeld number, welder or operator ID, WPS or weld schedule, date, material and heat numbers, examination resultQA/QC, daily, from crew sheets or machine data
Sample weld recordStart-of-shift or change-of-setup coupons, welder, resultQA/QC, if the owner requires sample welds
Examination recordVisual and borescope result, inspector, date, image referenceQA/QC
Repair recordOriginal weld, defect, repair weld number, re-examinationQA/QC

What good traceability looks like

  • Every weld in the field has its number marked as the specification requires, and the same number on the map.
  • Map and log match the current drawing revision; superseded welds are shown as such, not deleted.
  • Each welder ID in the log matches a valid qualification on the date of the weld.
  • Heat numbers in the log link to material certificates.
  • Borescope images can be found from the weld number.
  • Repairs and cut-outs keep the history of the original weld.

Where the owner and code decide

ASME B31.3 requires certain records to be kept, and owner specifications for fab piping usually add more, including the weld numbering format, sample weld rules, how orbital machine weld data is kept and in what form records are handed over. Some owners require a specific database or template. Ask for these before work starts; changing the numbering scheme mid-job is painful.

The foreman’s crew sheets are the usual input: the welder marks the weld number, their ID and the date at the joint, and the foreman’s daily sheet lists the welds completed. QA/QC reconciles the two with the examination results each day. When the numbers disagree, the log should show the question and its answer, not a silent correction.

Manual sheets, spreadsheets or software

Any of these can work if the data is complete and current. What matters is a single source of truth that one person owns. Ask a candidate which system they used, how they kept it current when the crew was ahead of the paperwork, and how they handled a drawing revision that renumbered welds.

Checking a candidate’s experience

Weld map and weld log management is one of the QA/QC skills listed on WELDK’s capabilities page. On a profile it is stated per candidate; ask for a sanitised sample of a log they kept and test the skill with the exercise in QA/QC interview questions. The logs feed directly into the turnover package.

Frequently asked questions

Who numbers the welds, the designer or the contractor?

It varies. Some owners issue isometrics with weld numbers; often the contractor adds them under the owner’s numbering rules. Check the specification.

Can orbital machine printouts replace the weld log?

They are a useful record of parameters, but they usually do not hold everything the log needs, such as heat numbers and examination results. Keep them linked to the weld number.

How quickly should the log be updated?

Daily is the usual practice. A log that trails the work by weeks is where traceability gaps appear.

Have a fab scope that needs these trades?