What a QA/QC inspector does on fab process piping

A contractor’s QA/QC inspector checks and records that the work meets the code, the owner specification and your quality plan: weld maps and logs, visual and borescope examination, welder qualification checks, test packages and nonconformance follow-up. They work for the contractor; the owner’s inspector is a separate role that verifies the contractor’s work on the owner’s behalf.

Contractor examiner and owner’s inspector

ASME B31.3 separates examination, which the contractor performs with qualified personnel, from inspection, which is the owner’s inspector’s job of verifying that the required examinations and tests were done. Your QA/QC hire sits on the examination side. On a fab project there may also be an owner’s QA team, a gas or chemical system specialist and a third-party inspector, each with their own sign-off.

Who signs what (typical; the quality plan and contract decide)
ActivityContractor QA/QCOwner’s inspector or owner QA
Weld map and weld logPrepares and keeps currentReviews, may sample
Visual and borescope examinationPerforms and records to the owner specificationWitnesses at agreed points
Welder and operator qualification recordsChecks before welding, tracks continuityAudits
Pressure and leak test packagesAssembles and presentsWitnesses and accepts
NonconformanceRaises, tracks, closes with evidenceAgrees disposition where required

Daily work on a UHP scope

  • Check each welder’s qualification and the WPS or weld schedule before the first production weld of a shift.
  • Record weld numbers, welder IDs, heat numbers and dates as work proceeds (weld maps and weld logs).
  • Examine sample and production welds to the owner’s visual criteria, often based on SEMI F81 for GTA welds, and keep borescope images (borescope records).
  • Verify purge, bagging and cleanroom handling at the workface.
  • Raise nonconformances and follow them to closure (handling an NCR).
  • Build the test and turnover packages (piping turnover package).

Where the owner spec and your QA manager decide

The owner specification sets the acceptance criteria, the examination extent and which records must be kept. Your QA manager decides who in your organisation may perform and sign each examination, and whether a particular inspector certification is required (see inspector certification). A QA/QC hire should be able to read the specification and tell you what it requires, but should not rewrite it.

Day to day, the QA/QC inspector is also the person who tells the foreman that a weld is rejected or a line cannot be tested yet. Ask how a candidate handled that on a past job: who they told, how quickly, and what record they made. An inspector who avoids the conversation, or who settles it informally without a record, creates audit problems later.

Writing the scope

WELDK’s capabilities page lists typical QA/QC experience as weld map and weld log management, visual and borescope inspection, test package and turnover documentation, and NCR follow-up. Say which of these your hire will own, which software or forms you use, and whether they will report to the site manager or to a QA manager off site.

Frequently asked questions

Can the contractor’s QA/QC inspector act as the owner’s inspector?

Not under the usual B31.3 arrangement, where the owner’s inspector represents the owner and is independent of the contractor’s examination. Your contract may describe the roles in more detail.

Does a QA/QC inspector do NDT such as radiography?

Usually not personally. Radiography and similar methods are normally done by certified NDT personnel or a subcontractor. Fab tube work relies more on visual and borescope examination, which QA/QC often performs.

Who should the QA/QC inspector report to?

Many contractors have QA/QC report to a QA manager rather than the site production lead, so that a schedule push cannot override a reject. Check what your quality plan and owner expect.