Site leadership and quality · Interviewing

Interview questions for a QA/QC inspector on UHP piping

Combine questions about the records the candidate kept with two practical exercises: judging real weld and borescope images against your owner’s criteria, and tracing a weld from the map to the log to the test package. A good UHP inspector explains what they would record and why, and knows when a decision belongs to the owner rather than to them.

Questions and what to listen for

QA/QC interview questions
QuestionGood answers includeWarning signs
Which specification and acceptance criteria did you inspect to last?Names the owner spec or standard and describes its main criteria“The usual standard”
How did you link each weld to its welder, material and date?Weld numbering, heat number records, log updated dailyRecords filled in at the end of the job
What do you check before a welder makes the first production weld of the shift?Qualification status, WPS or schedule, sample weld if the spec requires itNothing until the weld is finished
Tell me about an NCR you raised. How was it closed?Clear description, disposition agreed, evidence of closureNever raised one, or closed by verbal agreement
What goes into a test package you handed over?Isometrics, weld log, examination records, test records, punch listUnclear on contents
When would you call the owner’s inspector instead of deciding yourself?Hold points, disputed acceptance, deviations from the specNever, or for everything

Practical exercises

  1. Show six to ten photos of outside weld surfaces and borescope images of the inside, including acceptable and rejectable ones from your own site if you have them.
  2. Give the candidate the relevant acceptance criteria from the owner specification, often based on SEMI F81 for GTA welds.
  3. Ask them to accept or reject each one, state the reason and say what they would record.
  4. Then give a small isometric with weld numbers and a matching log with a few deliberate errors, and ask them to find the errors.

The exercise works by video for a candidate still in Korea, if you share the images and documents in advance or on screen.

Where your QA manager and the owner decide

Your QA manager sets the pass level for the exercises, decides whether a certification is required (inspector certification) and approves who may sign records. The owner specification sets the acceptance criteria. Do not let the candidate’s preferred standard replace the one your project uses.

Score the image exercise in two parts: whether the accept or reject decision matched your reference, and whether the reason and record were clear enough for an auditor. A candidate who reaches the right decision but cannot explain it will struggle when the owner questions a record. A candidate who is cautious and rejects a borderline weld, with a clear reason, is usually less risk than one who accepts it to keep work moving.

Questions for fab-specific judgement

  • What does heavy inside discoloration tell you about the purge, and who do you tell?
  • How do you store borescope images so they can be found for a specific weld later?
  • What do you do if a welder’s qualification is near its continuity limit?

Frequently asked questions

Where do we get images for the exercise?

Your own site records are best, with weld IDs removed. The Orbitalum handbook and SEMI F81 describe typical faults if you need to explain what each image shows.

Should QA/QC candidates take a weld test?

Not normally. Some employers ask them to watch a coupon weld and comment, which shows whether they know what to look for during welding.

What if the candidate inspected to a different owner’s specification?

That is common. Check whether they can read your specification and apply it; the habit of working to written criteria transfers.